Phase · 00

Before any system goes down

These five steps happen on every job, regardless of which system we install. They are the difference between a coating that lasts 15 years and one that fails in 18 months.

  1. Site walk & moisture test — calcium chloride or RH probes per ASTM F1869/F2170. We do not coat over wet slabs.
  2. Surface profile — diamond grinding to CSP 2–4 (most systems). Shot blasting on heavy commercial.
  3. Crack & joint repair — static cracks chase-cut and filled with polyurea; saw cuts honored or detailed per spec.
  4. Containment & masking — walls, fixtures, drains, and adjacent finishes protected before any product opens.
  5. Climate check — slab temp, ambient temp, dew point logged hourly during install.
System · 01

Epoxy Floor Systems

Two- or three-coat 100% solids epoxy build, optional decorative flake or quartz broadcast, finished with polyaspartic UV topcoat where exposure demands it.

  1. Day 1 AM — diamond grind to CSP 2–3, vacuum, repair static cracks.
  2. Day 1 PM — apply pigmented epoxy primer/basecoat at 8–12 mil.
  3. Day 2 AM — broadcast flake or quartz to refusal into wet base; let cure 8–12 hrs.
  4. Day 2 PM — scrape excess, vacuum, apply intermediate epoxy build coat.
  5. Day 3 AM — polyaspartic or urethane topcoat at 4–6 mil with optional anti-slip aggregate.
  6. Day 3 PM — walk-on after 8 hrs · light vehicle 24 hrs · full service 72 hrs.
Total install
2–3 days
Crew size
2–3 technicians
System thickness
40–60 mil
Walk-on cure
8 hours
Full chemical cure
5–7 days
Warranty
5 years labor + manufacturer
System · 02

Polyaspartic Coatings

One-day install. Polyaspartic basecoat, full flake broadcast, polyaspartic topcoat — back in service the next morning.

  1. 7:00 AM — diamond grind, vacuum, tape off perimeter.
  2. 9:30 AM — apply pigmented polyaspartic basecoat at 6–8 mil.
  3. 10:00 AM — broadcast decorative flake to full refusal into wet base.
  4. 12:30 PM — scrape, vacuum, knock down high spots with soft pad.
  5. 2:00 PM — apply clear polyaspartic topcoat at 4–6 mil.
  6. 5:00 PM — walk-on. Vehicle traffic next morning. Full cure 24 hrs.
Total install
1 day (8–10 hours)
Crew size
3 technicians
System thickness
20–30 mil
Walk-on cure
4–6 hours
Vehicle cure
24 hours
Warranty
15 years residential
System · 03

Metallic Epoxy

Custom-blended metallic pigments hand-troweled and back-rolled to create unique three-dimensional movement. Every floor is one-of-a-kind.

  1. Day 1 — diamond grind to CSP 3, full vacuum, tape and mask.
  2. Day 1 PM — apply pigmented epoxy primer in base color (black, white, or gray).
  3. Day 2 AM — mix metallic pigment into clear epoxy; pour, spread, and manipulate with rollers, leaf blowers, or solvent drops to create veining.
  4. Day 2 PM — let cure undisturbed 12 hrs (no foot traffic, no airflow disruption).
  5. Day 3 AM — light buff if needed, apply clear polyaspartic topcoat at 4–6 mil.
  6. Day 3 PM — optional second clear coat for extra depth.
  7. Day 4 AM — walk-on. Furniture next day. Full cure 5–7 days.
Total install
3–4 days
Crew size
2–3 (lead artisan + helper)
System thickness
30–40 mil
Pigment options
20+ standard, custom blends
Sample required
Yes — 2'×2' on-site mockup
Warranty
5 years labor
System · 04

Solid Color Epoxy

The simplest decorative system: one base color, no flake, no metallic. Common in warehouses, mechanical rooms, and back-of-house commercial spaces where a clean uniform finish matters more than visual drama.

  1. Day 1 AM — diamond grind to CSP 2, vacuum, repair cracks and joints.
  2. Day 1 PM — apply pigmented epoxy basecoat at 10–12 mil.
  3. Day 2 AM — light scuff sand, vacuum, apply pigmented epoxy topcoat at 8–10 mil.
  4. Day 2 PM — optional anti-slip aggregate broadcast into wet topcoat for wet areas.
  5. Day 3 AM — walk-on. Forklift / vehicle traffic at 48–72 hrs.
Total install
2 days
Crew size
2 technicians
System thickness
20–25 mil
Color options
30+ stock RAL colors
Walk-on cure
10–12 hours
Warranty
3 years labor
System · 05

Urethane Cement

Heavy-duty hybrid system for commercial kitchens, food & beverage plants, dairies, breweries — anywhere thermal shock, steam cleaning, and chemical exposure are daily realities.

  1. Day 1 AM — shot blast to CSP 4–5 (heavier profile required for cement bond).
  2. Day 1 PM — install integral cove base where required (4″ or 6″ up walls).
  3. Day 2 AM — trowel-apply urethane cement slurry at 1/4″ (250 mil) thickness.
  4. Day 2 PM — broadcast quartz aggregate to refusal for slip resistance.
  5. Day 3 AM — scrape excess, vacuum, apply pigmented urethane topcoat.
  6. Day 3 PM — apply chemical-resistant urethane sealcoat.
  7. Day 4 AM — walk-on. Wet cleaning at 24 hrs. Full chemical cure 7 days.
Total install
3–4 days
Crew size
4 technicians (trowel work)
System thickness
1/4″ (250 mil)
Thermal shock
Resistant to 250°F differential
USDA / FDA
Compliant (food contact)
Warranty
5 years labor
System · 06

Polished Concrete

The slab itself is the finish. Progressive diamond grinding from coarse (40-grit) to fine (1500–3000 grit) plus densifier and stain-resistant sealer. No coating to peel, ever.

  1. Day 1 — initial cut: 40-grit metal-bond diamonds expose desired aggregate level (cream, salt-and-pepper, or full aggregate).
  2. Day 1 PM — step up through 80 and 150 grit metal bonds.
  3. Day 2 AM — apply lithium silicate densifier; let dwell & absorb.
  4. Day 2 PM — resin-bond polish: 100, 200, 400 grit.
  5. Day 3 AM — resin-bond polish: 800, 1500 grit (3000 grit optional for ultra-gloss).
  6. Day 3 PM — apply stain-guard sealer (penetrating, no surface film).
  7. Day 4 AM — burnish to final sheen. Walk-on immediately.
Total install
3–4 days
Crew size
2 technicians
Final sheen
Satin / semi / high-gloss
Aggregate exposure
Cream / salt-and-pepper / full
Walk-on
Immediate
Lifespan
20+ years (re-burnish as needed)
System · 07

Concrete Overlay

A thin polymer-modified cement layer poured over existing concrete. Stamped, broomed, or troweled to mimic flagstone, slate, brick, or smooth modern finishes — without tearing out the slab underneath.

  1. Day 1 AM — pressure wash, etch, or grind existing slab to open the surface.
  2. Day 1 PM — repair spalls, fill divots, apply bonding primer.
  3. Day 2 AM — place forms / control joints; mix and pour polymer-cement overlay 1/4″–3/8″ thick.
  4. Day 2 PM — stamp pattern (flagstone, ashlar slate, wood plank, custom) while overlay is plastic.
  5. Day 3 AM — apply integral or topical color hardener; broom or texture as designed.
  6. Day 3 PM — let cure undisturbed 24 hrs.
  7. Day 4 — apply UV-stable acrylic or urethane sealer (2 coats).
  8. Day 5 — walk-on. Vehicle traffic at 7 days.
Total install
4–5 days
Crew size
3–4 technicians
Overlay thickness
1/4″ – 3/8″
Patterns
Stamped / troweled / broomed
Best for
Patios, pool decks, driveways, walkways
Reseal
Every 2–3 years
System · 08

Repair & Sealing

For slabs that don't need a new coating — just a tune-up. Crack repair, joint filling, surface densification, and penetrating sealer to extend the life of an existing concrete or coated floor.

  1. Day 1 AM — assess: identify cracks (static vs active), failed joints, surface dusting, stains.
  2. Day 1 PM — chase-cut static cracks; vacuum debris.
  3. Day 1 late — fill cracks with semi-rigid polyurea; trim flush.
  4. Day 2 AM — reseal control joints with self-leveling polyurea.
  5. Day 2 PM — apply lithium silicate densifier (if surface is dusting).
  6. Day 2 late — apply penetrating siloxane or stain-guard sealer.
  7. Day 3 AM — walk-on immediately. Vehicle 24 hrs.
Total install
1–2 days
Crew size
2 technicians
Best for
Existing slabs in fair shape
Adds
3–7 years of service life
Disruption
Minimal — most rooms stay usable
Warranty
2 years labor
Phase · 09

After we leave the jobsite

Final cure, walkthrough, documentation. Same on every system.

  1. Final walkthrough — punch-list signed by you, on-site.
  2. Care & cleaning kit — printed maintenance schedule, recommended cleaners, contact for refresh.
  3. Warranty packet — labor warranty + manufacturer datasheet, emailed PDF.
  4. 12-month check-in — we follow up to inspect and re-burnish or seal-touch-up at no charge.

Ready to scope your job?

Tell us the slab, the use case, and the deadline. We'll come measure, test, and quote at no charge.